2024 Street Resurfacing Projects
The following streets are scheduled for resurfacing during the 2024 Construction Season:
Project Roadway | Project Beginning | Project End | Type of Resurfacing |
Spring Avenue | 4th Street | Washington Ave | Overlay |
L Avenue | 2nd Street | 1st Street | Overlay |
Spring Avenue | 2nd Street | 4th Street | Overlay |
Benton Avenue | Union Street | Walnut Street | Overlay |
15th Street | H Avenue | Washington Avenue | Overlay |
Willow Street | Cove Avenue | East L Avenue | Overlay |
6th Street | K Avenue | C Avenue | Overlay |
Monroe Avenue | Fir Street | the Railroad Tracks (Island Ave) | Overlay |
Harrison Avenue | End of Road | 2nd Street | Overlay |
Division Avenue | Union Street | North 2nd Street | Overlay |
V Avenue | Spruce Street | Willow Street | Overlay |
Z Avenue | Spruce Street | Cherry Street | Overlay |
Crook Avenue | Cedar Street | 2nd Street | Overlay |
12th Street | Washington Avenue | Top of the Hill (F Street) | Grind and Inlay |
N Avenue | 4th Street | Washington Avenue | Grind and Inlay |
Walnut Street | N Ave | Adams Avenue | Grind and Inlay |
Notes:
- Projects will not necessarily be completed in the order presented
- There are no established start dates for projects as work is weather dependent and may be scheduled around other work depending on priorities
- Additional projects will be added as preparations for resurfacing are completed
- Projects will be removed from the above list as they are completed