- September 4, 2012
- Veterans' Memorial Pool Closure
-
Pool Repair in Progress
Read More- Comments(0)
- August 31, 2012
- Big H Streetscape Project - Weekly Update - Sept. 3-7, 2012
-
Again this week there will be miscellaneous finish work throughout the project area and alley reconstruction prep work. There will be no project work on Monday, Sept. 3 due to the Labor Day holiday. New bolt-in amenities (benches, trash cans & planters) are being placed throughout the project.
Concrete work will occur on the north side of Adams near Sterling Bank and on Washington between Depot and the public parking lot. Pedestrian ramps will be finished on Jefferson.
There will be closures affecting both alleys between Depot & Elm. The sidewalk is closed on Washington between Depot and the public parking lot and on Adams near Sterling Bank. Two pedestrian ramps are closed on Jefferson.
Read More
- Comments(0)
- Ghost Hunters Northwest Project Spooky
PROJECT SPOOKY is Ghost Hunters Northwest's educational program for anybody interested in the Paranormal Field. G.H.N.W. offers Class Presentations that educate groups in the Paranormal Field and how Paranormal Investigations are conducted. This Project is directed for anyone who is interested in the in what G.H.N.W. and teams like it do in the Paranormal Field.
Read More- Comments(0)
- August 23, 2012
- Big H Streetscape Project Weekly Update - Aug. 27-31
-
There will be miscellaneous finish work throughout the project area and alley reconstruction prep work on the two alleys between Depot & Elm. Concrete replacement will occur on the north side of Adams near Sterling Bank and on Washington between Depot and the public parking lot. Pedestrian ramps will be finished on Adams and on Jefferson. The major impacts will be temporary alley closures throughout the project area. Most on street parking has been restored.
Read More
- Comments(0)
- August 16, 2012
- Big H Streetscape Project Weekly Update - Aug. 20-24, 2012
-
Impacts will be light this next week as the contractor focuses primarily on finish work throughout the project area. The main areas of impact will be concrete work near Sterling Bank on Adams, the sidewalk and alley adjacent to BELLA and Cherry’s florist on Elm and the sidewalk to the rear of the Reynolds Bldg. on Washington. Most on-street parking should return throughout the project area next week.
Read More- Comments(0)